Thursday, March 21, 2013

Milwaukee area not aesthetic enough to bury power lines

I guess the logic goes something like this: it's already developed and therefore aesthetically compromised, so more development in the form of overhead power lines won't matter to people who live in the Milwaukee area. Or, to be more precise, in Wauwatosa, near Underwood Parkway and the Milwaukee County Grounds.

According to an article in yesterday's Journal Sentinel, "'Selecting another route would shift millions of dollars of extra costs for underground lines to ratepayers in the ATC footprint far removed from the Milwaukee area, who would not benefit from a more aesthetically pleasing project area,' the commission's decision says."

 The short-sighted decision by the Public Service Commission disturbed many in the region who have worked very hard to support alternative routes.

The City of Wauwatosa is one of the stakeholders considering what further options, including the possibility of legal action, may be used to challenge this decision. (May the odds be ever in their favor!)

If you go to the article in the Journal Sentinel you will see a map that isn't completely accurate. I learned today at a meeting for County Grounds stakeholders that the section shown crossing the County Grounds will actually turn at Hwy 45 and run south to Watertown Plank Rd. where it will follow the dashed line to the substation. The correct map is below.

     

Tuesday, March 12, 2013

The trees lose again!


Many people in Wauwatosa, as well as others who frequent the County Grounds, are still in shock at the loss of trees there. Prepare yourselves! If you drive along this stretch of Highway 100 south of Watertown Plank Road you will see that here too the highway is winning and the trees losing.

In this case, it is due to the widening of Hwy 100 that is being done to accommodate a projected increase in traffic during the Zoo Interchange reconstruction. Of course, it won't be narrowed again once that project is completed.

Wauwatosa is among the many cities that pride themselves on being a Tree City. How many stumps does it take to lose that designation, I wonder? I hope it doesn't come to that.

I want to thank Cheryl Marlega, one of the staunchest supporters of the Friends of the Monarch Trail for sharing the following link to a video about the tree cutting on the County Grounds. It is called, "In Memory of the Trees." If you were among the many who were moved by my post on that subject, you will want to check out this link: "In Memory of the Trees."

All is not completely gloom and doom, however. We Energies has just unveiled its plan for the new substation to be built on the County Grounds. It will be sited to the west of the existing plant in what is currently an open field, as indicated in orange on the map. This is a better location than the other alternative, north of the plant, which is still woodland and butler garter snake habitat - among other wildlife species! So, here is a case where the trees have been saved for the time being. A Tree City ought to be able to protect them in perpetuity, don't you agree?

Friday, March 1, 2013

PSC decision: power lines belong in Underwood Parkway

-->
Tragic news today. The Public Service Commission ignored all the efforts by all the agencies, organizations, city and county officials, community groups, and individuals to preserve Underwood Parkway from overhead power lines. Considering all the testimony that's been presented to them from all the varied constituencies, a neutral observer could be forgiven for wondering what public the Public Service Commission serves.

All they care about is the money. The short-sighted decision is excerpted below. If you want to read the full press release go to the PSC website.


The PSC press release says:

"The Commission-approved routes for the project are as follows:

"East-West Section: The route begins at a proposed interconnection point located near 120th Street and West Diane Drive in the Underwood Parkway. Route B(1) lies north of and parallel to Underwood Creek and the CP railroad until it crosses to the south side of the creek at 115th Street. The route continues, following Underwood Creek, crossing the UP railroad, Watertown Plank Road, and STH 100. The route then turns and continues east, crossing the USH 45 freeway, and then parallels the east side of the freeway south to Watertown Plank Road. Turning east, the route follows the north side of the street until it reaches a point just south of the proposed MC Substation site.

"North-South Section: The route begins at the 96th Street Substation and follows the east edge of the USH 45 freeway ROW behind the Parkside Pool Apartments, the Montessori School, and St. Therese Church properties north to Watertown Plank Road, crossing Bluemound Road and Wisconsin Avenue. While the Commission will return to decide where undergrounding will begin at this section, the route will eventually reach a point just south of the proposed substation site. The route then turns to proceed north into the substation.

"All documents associated with the application may be found at the Commission's web site, http://psc.wi.gov, by typing in docket number 5-CE-139 into the Electronic Regulatory Filing System."

Read blogger Chris McLaughlin's response here. It's good.